Case Study

OMEX Agriculture Fertilizer Plant Warehouse

Client:

Bristol Port Company

Project Duration:

8 weeks

Scope of Project Works

Installation of new 11kV Substation to supply new OMEX Agriculture Fertilizer Plant warehouse comprising of construction of a new substation base with GRP Kiosk Installation, a new 11kV transformer with close coupled RMU & close coupled LV ACB Cabinet, associated HV/LV cabling including HV cable diversion and installation and LV main cabling