Case Study

Gatherley RWPs

Client:

Kier

Project Duration:

36 weeks

Scope of Project Works

To supply, install and commission a new remote, Private HV intake fed from a new DNO metered supply.  Supply, install and joint 5 km of HV cable to the location of a new Raw Water Pump Station.

A local HV ring was installed, protected by a RMU that serviced 4 new 11000/690v transformers, and 1 11000/415v Transformer for local supplies.

The supply and installation of the LV single cored cables between the close coupled LV ACB cabinets and the internal Incoming LV switchboards.