Case Study

Churchill Block

Client:

Lorne Stewart

Project Duration:

16 weeks

Scope of Project Works

To supply and install a new 11kV substation to an existing HV network, servicing a newly purposed building.

To carry out the civil engineering and building works for the new substation base.

Supply the GRP enclosure and the associated lights and power

To undertake the installation of the new earth mat